Critical paths and scheduling

Introduced
Watch lesson
Vocabulary
English Meaning
critical path methodA method that finds the activities that control how long a project takes.
activity networkA diagram that shows a project's activities and the order in which they must be done.
precedence tableA table listing each activity of a project and the activities that must be finished before it.
dummy/ˈdʌmi/A zero-duration activity arc used to represent a dependency in an activity-on-arc network.
critical/ˈkrɪtɪkl/Describes an activity whose delay would delay the whole project; its float is zero.
float/fləʊt/The time an activity can be delayed without delaying completion under the network model.
total float/ˈtəʊtl fləʊt/The delay available to an activity without delaying project completion: latest finish minus earliest start minus duration.
Gantt chart/ɡænt tʃɑːt/A bar chart showing scheduled activities and their timing along a time axis.