Decision Mathematics 1

Pearson Edexcel · International A-Level · Mathematics Topic 9 4:04 English narration · English + 中文 subtitles burned in

space play · ←/→ 5s · j/l 10s · f fullscreen · ,/. speed

Chapters

Transcript
Paper WDM01: 1 hour 30 minutes, 75 marks. WDM01 试卷:1 小时 30 分钟,75 分。
Every method is an algorithm, and the marks are for executing it exactly: the list after each pass, each placement, the order edges are chosen, the pairings before the total, and every constraint. 每种方法都是算法,分数给的是准确执行:每一轮之后的列表、每一次放置、选边的顺序、先写配对再写总数,以及每一个约束。
Sort 9, 2, 7, 5, 3, 4, 6. 对 9, 2, 7, 5, 3, 4, 6 排序。
The middle item is the pivot 5: smaller items go before it, larger after, in their original order. 中间项 5 是基准:较小的放在前面,较大的放在后面,保持原有顺序。
Then pivots 3 and 7 split the two sublists, and every item is fixed. 然后基准 3 和 7 分割两个子列表,所有项都确定了位置。
A bubble sort instead swaps neighbours until a pass makes no swaps. 冒泡排序则交换相邻项,直到某一轮没有交换。
Items 7, 5, 4, 3, 6, 2 in bins of 10. 物品 7, 5, 4, 3, 6, 2,箱子容量 10。
First-fit puts each in the first bin with room: 5 will not join 7, so it opens bin 2; 3 then fills bin 1. 首次适应法把每个物品放进第一个放得下的箱子:5 放不进装 7 的箱子,于是开第 2 个箱子;3 随后填满第 1 个箱子。
First-fit decreasing sorts largest first; full-bin packing looks for exact tens. 首次适应递减法先从大到小排序;满箱法寻找恰好凑成 10 的组合。
Edges AB 4, AC 2, BC 3, BD 5, CD 1. 边 AB 4、AC 2、BC 3、BD 5、CD 1。
Kruskal takes the cheapest first: CD 1, AC 2, BC 3, and every vertex is joined. 克鲁斯卡尔先取最便宜的:CD 1、AC 2、BC 3,所有顶点都连上了。
It then rejects AB 4 and BD 5, which would make cycles. 然后拒绝 AB 4 和 BD 5,它们会形成环。
Prim from A grows the same tree. 从 A 出发的普里姆算法得到同一棵树。
Now BC 1, CD 8. 现在 BC 1、CD 8。
A is 0, then C is 2. A 为 0,然后 C 为 2。
B is the smaller of 4 and 2 plus 1: B is 3. B 取 4 与 2 + 1 中较小者:B 为 3。
D is the smaller of 3 plus 5 and 2 plus 8: D is 8. D 取 3 + 5 与 2 + 8 中较小者:D 为 8。
Trace back where a label equals the next minus the edge: A, C, B, D. 沿“标号等于下一个标号减边权”回溯:A、C、B、D。
Edges AB 4, AC 2, BC 3, BD 5, CD 1 total 15. 边 AB 4、AC 2、BC 3、BD 5、CD 1,总长 15。
Every vertex must be even to walk each edge and return; B and C are odd, so duplicate BC, weight 3. 要走遍每条边并回到起点,每个顶点必须是偶数度;B 和 C 是奇数度,所以重复 BC,权 3。
The shortest closed route is 18. 最短闭合路线为 18。
With four odd vertices, compare all three pairings. 有四个奇点时,比较全部三种配对。
Nearest neighbour from A gives A, C, B, D, A: a tour of 17, an upper bound. 从 A 出发的最近邻算法得到 A、C、B、D、A:长度 17 的回路,是一个上界。
Doubling the tree gives a cruder 20. 把最小生成树加倍得到更粗的 20。
Deleting A, the tree on B, C, D is 8, plus A's two cheapest edges, 6: a lower bound of 14. 删去 A,B、C、D 的生成树为 8,加上 A 的两条最便宜的边 6:下界 14。
Activities A 3 and B 4 start the project; C follows A, D follows B, and E follows both. 活动 A 3 和 B 4 开始项目;C 在 A 之后,D 在 B 之后,E 在两者之后。
The earliest event times run 0, 3, 4, 7, 12. 最早事件时间依次为 0、3、4、7、12。
The critical path is A, C, E, the longest chain: 12 days; B, D, E takes only 10. 最长的链即关键路径 A、C、E,共 12 天;B、D、E 只要 10 天。
Bar each activity from its earliest start. 每个活动从最早开始时间画一条横条。
The critical activities, A, C and E, run end to end with no gap. 关键活动 A、C、E 首尾相接、没有空隙。
D can slip: its float is 2 days, drawn as the space after it. D 可以推迟:它的总时差是 2 天,画在它后面的空白处。
Shade the feasible region bounded by both constraints and the axes. 画出由两个约束和坐标轴围成的可行域。
Then slide the objective line, 3x plus 2y, outwards: the last point it touches is the vertex 4, 6, where both constraints are tight and P is 24. 然后把目标线 3x + 2y 向外平移:它最后接触的点是顶点 (4, 6),两个约束都取等号,P = 24。
List the vertices of the region. 列出可行域的顶点。
The corner where the constraints cross solves x plus y equals 10 and 2x plus y equals 14: 4, 6. 约束交点由 x + y = 10 和 2x + y = 14 解得 (4, 6)。
Evaluate P at each vertex: 0, 21, 24, 20. 在每个顶点计算 P:0、21、24、20。
The maximum is 24. 最大值是 24。
Check yourself. 自我检测。
The quick sort pivot is the middle item. 快速排序的基准是中间项。
Kruskal rejects an edge that makes a cycle. 克鲁斯卡尔拒绝会形成环的边。
The postman duplicates the least pairing of odd nodes. 邮递员问题重复奇点配对中最短的那一组。
A lower bound deletes a vertex. 下界要删去一个顶点。
And critical activities have zero float. 关键活动的总时差为零。