Skip to content

IGCSE Physics · November 2022 · Paper 23 · Difficulty 5 · Stretch

Question 9

9

A skier is pulled up a short straight slope at constant speed by a rope.

The tension in the rope is 100 N and there is a combined frictional and air resistance force of 20 N acting on the skier.

The slope is 10 m long and the skier rises 1.5 m vertically.

How much work is done by the rope pulling the skier up the slope?

A

120 J

B

150 J

C

1000 J

D

1200 J

Choose an option to check your answer.

Show the answer

Answer: C

  • Work done = force $\times$ distance moved in the direction of the force.
  • The rope pulls with 100 N along the slope, and the skier moves 10 m along the slope.
  • $W = 100 \times 10 = 1000$ J. The 20 N friction and the 1.5 m height are not needed here.