The second site runs a festival contract: batches of 120 buns, 480 buns an hour, 19,200 a week. 第二个生产点承接了一份节庆活动合同:每批 120 个面包,每小时 480 个,每周 19,200 个。
That one line carries the course. 整门课都围绕这条生产线展开。
The habit is to find the constraint, measure the error, and state the boundary. 我们要养成的习惯是找出瓶颈、衡量误差,并明确边界。
Seven units follow: capacity, quality, inventory, forecasting, supply chains, projects, and sustainability. 接下来有七个单元:产能、质量、库存、预测、供应链、项目和可持续性。
A line runs at its slowest station. 生产线的运行速度取决于最慢的工序。
Mixing takes 12 minutes, so 5 batches an hour. 和面需要 12 分钟,因此每小时可完成 5 批。
Proofing manages 7.5, baking 6.67, and packing 10. 发酵每小时可完成 7.5 批,烘烤为 6.67 批,包装为 10 批。
So mixing is the bottleneck, the cycle time is 12 minutes, and the line makes 600 buns an hour. 所以和面是瓶颈,周期时间为 12 分钟,生产线每小时生产 600 个面包。
At 4 batches an hour, Little's law says 4 batches are inside the line at once. 当每小时生产 4 批时,根据利特尔法则,生产线上同时有 4 批在制品。
Saturday needs 6 batches an hour for 8 hours, but one mixer caps the line at 5. 星期六的需求是连续 8 小时每小时 6 批,但一台和面机将生产线产能限制在每小时 5 批。
That is one batch short every hour, 8 over the day. 这意味着每小时少 1 批,全天少 8 批。
A second mixer would let baking clear 6 at 6.67, but that is capital for one day a week. 增加一台和面机后,烘烤工序每小时能完成 6.67 批,足以应付 6 批的需求,但为每周一天的需求投入资本并不划算。
Instead, bake ahead: two Friday hours at 5 an hour give 10 batches, covering the 8. 可以提前烘烤:星期五用 2 小时按每小时 5 批生产,就能得到 10 批,足以补足这 8 批。
Sample means of bun weight run at 80 grams, plus or minus 2.68: three sigma over root five, with sigma 2. 面包重量的样本均值控制界限为 80 克上下 2.68 克:也就是 3 倍标准差除以根号 5,标准差为 2。
So a mean of 82.9 is a special cause, and eight points below centre is a shift. 所以均值为 82.9 表明存在特殊原因,而连续 8 个点位于中心线以下则表明过程发生了偏移。
Within the limits, hands off: retuning is tampering. 在控制界限内不要干预:重新调整属于不必要的干扰。
Inspection finds bad buns after the fact; the chart finds the batch going bad. 检验是在事后找出不合格面包;控制图则能发现正在出现问题的批次。
One week brings 86 defects: underweight 46, damaged 21, then a few others. 一周内出现 86 个缺陷:重量不足 46 个,破损 21 个,另外还有少量其他缺陷。
The Pareto shows that 67 of 86, 77.9 per cent, sit in two causes, and underweight traces to one filler head. 帕累托图显示,86 个缺陷中有 67 个,也就是 77.9%,来自两种原因,而重量不足可追溯到一个灌装头。
The cost of quality is 19,000 pounds, and 81 per cent of it is failure. 质量成本为 19,000 英镑,其中 81% 是故障成本。
Prevention at the front is the cheap quality. 在前端做好预防,才是成本低的质量保障方式。
Ordering and holding pull against each other. 订货成本和持有成本此消彼长。
The economic order quantity is the root of 2 times 48,000 times 50, over 1.20: 2,000 kilograms. 经济订货量是 2 乘以 48,000 再乘以 50,除以 1.20 后开平方,结果为 2,000 千克。
That means 24 orders, with 1,200 pounds of ordering and 1,200 of holding. 这意味着订货 24 次,订货成本为 1,200 英镑,持有成本也为 1,200 英镑。
Daily demand is 131.5 kilograms with a six-day lead time, so 789 plus 101 of safety stock gives a reorder point of 890. 日需求量为 131.5 千克,提前期为 6 天,因此提前期需求 789 千克加上 101 千克安全库存,得到再订货点 890 千克。
Stock falls steadily as it is used. 库存随着使用而稳定下降。
When it reaches the re-order level, an order is placed. 当库存达到再订货水平时,就发出订单。
During the lead time, stock keeps falling. 在提前期内,库存继续下降。
Then the delivery arrives and stock jumps back to the maximum. 随后货物送达,库存迅速回升到最高水平。
The buffer stock is a safety cushion, in case demand is higher or the delivery is late. 缓冲库存是安全保障,以防需求增加或交货延迟。
The mill offers 2 per cent off for orders of 4,000 kilograms. 面粉厂对 4,000 千克的订单提供 2% 的折扣。
At the economic quantity, the total cost is 98,400. 按经济订货量订货时,总成本为 98,400。
At 4,000, purchase falls to 94,080, ordering to 600, and holding rises to 2,400: a total of 97,080, saving 1,320. 订购 4,000 千克时,采购成本降至 94,080,订货成本降至 600,持有成本升至 2,400:总计 97,080,节省 1,320。
The extra logistics cost exactly 600, so any discount above 0.625 per cent pays. 额外物流成本恰好是 600,因此只要折扣超过 0.625% 就划算。
Check total cost, or not at all. 一定要比较总成本。
Demand rose from 420 to 600 over eight weeks. 需求在 8 周内从 420 上升到 600。
Score methods by mean absolute deviation on the same weeks: naive 37.1, a three-week moving average 52.0, and smoothing 48.3. 用相同几周的平均绝对偏差来评价各方法:简单预测法为 37.1,3 周移动平均法为 52.0,指数平滑法为 48.3。
The average lags a trend. 移动平均会滞后于趋势。
The least-squares line, 395.7 plus 24.3 per week, gives 614 for week nine, plus or minus 19. 最小二乘趋势线为 395.7 加上每周 24.3,给出的第 9 周预测值是 614,上下浮动 19。
Fit the shape, then quote a band. 先拟合趋势形态,再给出一个区间。
Sales hears of a second festival stage. 销售部门得知节庆活动将增设第二个舞台。
So the forecast becomes 614 times 1.1, which is 675, written down as a judgemental uplift with its reason, its owner and its date. 于是预测值调整为 614 乘以 1.1,即 675,并将其记录为判断性上调,同时注明原因、负责人和日期。
Actual demand was 700: the adjusted number was 25 low, while the bare 614 would have been 86 low. 实际需求为 700:调整后的数字低估了 25,而未经调整的 614 会低估 86。
Judgement is allowed; hidden judgement is not. 可以运用判断,但不能隐瞒判断。
Mill B charges 1.90 a kilogram, saving 4,800 on price but costing 1,262 to hold the longer pipeline. 面粉厂 B 每千克收费 1.90,采购价格上节省 4,800,但更长的在途周期带来 1,262 的持有成本。
That is a net gain of 3,538, but it is on time only 92 per cent of the time, so the split is 70 per cent A and 30 per cent B. 净收益为 3,538,但它的准时交货率只有 92%,因此采购分配为 A 占 70%、B 占 30%。
Pooling two depots' safety stock cuts 987 kilograms to 698, by 29.3 per cent. 合并两个配送中心的安全库存后,库存从 987 千克降至 698 千克,减少了 29.3%。
Four pack formats each carry their own forecast error. 四种包装规格各自都有预测误差。
Pack at the depot instead, and the generic buns carry one forecast, so safety stock halves, from 1,316 to 658. 如果改在配送中心包装,通用面包只需要一个预测,因此安全库存减半,从 1,316 降至 658。
That is the pooling law in time instead of space. 这是把库存集中化原理从空间应用到时间上。
The depot packing line costs 18,000, write-offs fall by about 15,600 a year, and the payback is 14 months. 配送中心的包装线成本为 18,000,每年报废损失减少约 15,600,回收期为 14 个月。
The critical path, A B C D F H, runs 18 days; task E floats 5 days, and G floats 1. 关键路径 A B C D F H 历时 18 天;任务 E 的总时差为 5 天,G 为 1 天。
Crash C by two days at 400 a day, and D by one at 600, against a day's value of 700: the project falls to 15 days for a net gain of 700. 将 C 缩短 2 天,每天成本 400;将 D 缩短 1 天,成本 600,而节省一天的价值为 700:项目缩短至 15 天,净收益为 700。
Crash only where the path runs, and only below the value of a day. 只压缩关键路径上的任务,而且每天的压缩成本必须低于节省一天的价值。
On day 10 of 18, the project has spent 36,400 pounds of a 60,000 budget, with half the scope done. 在 18 天项目的第 10 天,60,000 的预算已花费 36,400 英镑,工作范围完成了一半。
Earned value is 30,000. 挣值为 30,000。
So the cost index is 30,000 over 36,400, 0.824, and the schedule index is 0.909. 因此成本绩效指数是 30,000 除以 36,400,等于 0.824,进度绩效指数为 0.909。
The estimate at completion is 72,800, a 12,800 overrun. 完工估算为 72,800,超支 12,800。
Spend is not progress: 61 per cent of the money bought 50 per cent of the value. 花费不等于进度:花了 61% 的资金,只完成了 50% 的价值。
In a critical path network, each node shows the earliest start time and latest finish time. 在关键路径网络图中,每个节点显示最早开始时间和最迟完成时间。
Activities with zero float lie on the critical path. 总时差为零的活动位于关键路径上。
Any delay to one of them delays the whole project, so they need the closest management. 其中任何一项活动延迟,都会使整个项目延迟,因此需要最密切地管理。
A footprint means nothing without its boundary. 碳足迹如果没有明确边界就没有意义。
Gate to gate, electricity, gas and vans give 2,492 kilograms of carbon a week, 130 grams a bun. 在厂区进出边界内,电力、燃气和货车每周产生 2,492 千克碳排放,每个面包 130 克。
Cradle to gate adds 508 kilograms of flour, making 3,000, 156 grams a bun. 从摇篮到出厂的边界再加上面粉带来的 508 千克,总计 3,000 千克,每个面包 156 克。
A renewable tariff halves the site figure to 1,244 and leaves the flour alone. 采用可再生能源电价方案,可使厂区排放量减半至 1,244,但面粉的排放量不变。
Compare footprints only inside one boundary. 比较碳足迹时,必须使用相同的边界。
Scope 1 covers emissions the firm makes directly, such as gas for its ovens and fuel for its own vans. 范围 1 涵盖企业直接产生的排放,例如烤箱使用的燃气和自有货车使用的燃料。
Scope 2 covers the electricity it buys. 范围 2 涵盖企业购买的电力。
Scope 3 covers everything else in the chain, such as flour and packaging from suppliers. 范围 3 涵盖供应链中的其他排放,例如供应商提供的面粉和包装材料产生的排放。
For many firms, Scope 3 is the largest, and the hardest to measure. 对许多企业来说,范围 3 的排放量最大,也最难衡量。
Cardboard trays cost 9,240 pounds a year. 纸板托盘每年成本为 9,240 英镑。
Returnable trays cost 5.50 each. 可回收使用的托盘每个成本为 5.50。
With 98 per cent returned, losses and washing cost 6,090, saving 3,150, with a payback of 2.8 years. 在回收率为 98% 时,损耗和清洗成本为 6,090,节省 3,150,回收期为 2.8 年。
At 95 per cent, losses alone are 11,550, and the scheme loses 3,780 a year. 回收率为 95% 时,仅损耗成本就达到 11,550,该方案每年亏损 3,780。
The breakeven is 96.6 per cent: the whole decision is the loss rate. 保本回收率为 96.6%:整个决策取决于损耗率。
One project sheet holds the whole course: capacities of 5, 7.5, 6.67 and 10 with mixing the bottleneck; limits of 80 plus or minus 2.68; an order quantity of 2,000 and a reorder point of 890; a week-nine forecast of 614; a pooled stock of 698; an 18-day path with a forecast cost of 72,800; and 2,492 kilograms of carbon. 一张项目表概括了整门课:各工序产能为 5、7.5、6.67 和 10,和面是瓶颈;控制界限为 80 上下 2.68;订货量为 2,000,再订货点为 890;第 9 周预测值为 614;合并后的库存为 698;关键路径为 18 天,预测成本为 72,800;碳排放量为 2,492 千克。
Now test yourself from memory. 现在凭记忆测试一下自己。
What are the bottleneck and the cycle time? 瓶颈是什么,周期时间是多少?
What are the control limits and the order quantity? 控制界限和订货量分别是多少?
What are the week-nine forecast and the critical path? 第 9 周的预测值和关键路径是什么?
And what are the gate-to-gate and cradle-to-gate footprints? 厂区进出边界内的碳足迹和从摇篮到出厂的碳足迹分别是多少?
Pause, answer each one, then recompute. 暂停视频,逐一作答,然后重新计算。