コンテンツへスキップ

Project management: the critical path is the project

導入済み
プリント
語彙
English 意味
critical path/ˈkrɪtɪkl pæθ/The longest chain of linked tasks in a project; a delay on it delays the whole project.
total float/ˈtəʊtl fləʊt/how long an activity can slip without delaying the whole project
crashingshortening critical activities by spending money on them
earned value analysistracking a project with planned, actual and earned value and the ratios between them

プリント

ログインまたはアカウント作成

IGCSE, A-Level & AP